Advances in Energy Sciences and Technologies

Advances in Energy Sciences and Technologies

Beyond levelized cost: Risk-informed full-system screening of Iran’s electricity pathways—Iran Hormoz nuclear case study

Document Type : Original Article

Authors
1 Department of Energy Engineering and Physics, Amirkabir University of Technology (Tehran Polytechnic), P.O. Box 15875-4413, Tehran, Iran
2 Department of Mechanic & Energy, Islamic Azad University, Central Tehran Branch, Tehran, Iran
3 Nuclear Science and Technology Research Institute (NSTRI), P.O. Box: 14155-1339, Tehran, Iran
10.22060/aest.2026.26511.1014
Abstract
Levelized cost of electricity (LCOE) is useful for initial technology screening, but it does not fully represent the cost or value of delivering comparable electricity-system services. This study develops a risk-informed full-system screening framework for Iranian electricity pathways and applies it to the four-unit Iran Hormoz Nuclear Power Project (IHNPP). The framework distinguishes annual-energy equivalence from system-service equivalence, separates bankable project cash flow from wider national economic value, and incorporates project-specific delivery risk without claiming a chronological power-system optimization.
IHNPP comprises four nominal 1,255-MWe units with 5,020 MWe of gross capacity. Under a 93% production factor and 10% internal electricity consumption, annual generation is 40.90 TWh gross and 36.81 TWh net. Matching this net annual output requires approximately 6.00 GW of CCGT at a 70% net capacity factor, 14.01 GW of onshore wind at 30%, or 18.27 GW of solar PV at 23%. Sensitivity over an IHNPP production-factor range of 85–95% changes net generation from 33.64 to 37.60 TWh/y.
The economic screening adopts a total CAPEX of USD 25.0 billion, equivalent to approximately USD 4,980/kW gross, with annual OPEX and overhaul expenditure of USD 441.70 million. At USD 0.05/kWh, annual electricity-sale revenue is approximately USD 1.84 billion. Deterministic sensitivity tests examine CAPEX, tariff, production factor, financing conditions, and construction delay. The project register contains 309 risks, of which 73 (23.6%) are Super Critical or High; financial and economic risks account for 35.6% of this priority subset.
The results indicate that technology ranking cannot be inferred from LCOE or annual energy alone. For IHNPP, economic performance remains strongly conditioned by financing, project delivery, contractual arrangements, and grid integration.

Graphical Abstract

Beyond levelized cost: Risk-informed full-system screening of Iran’s electricity pathways—Iran Hormoz nuclear case study
Keywords
Subjects

Volume 2, Issue 1
Summer 2026
Pages 85-105

  • Receive Date 13 August 2026
  • Revise Date 08 September 2026
  • Accept Date 16 September 2026
  • Publish Date 01 July 2026